The Year of the Community Infrastructure Levy
January 31, 2012
Debates over viability and value capture are an inevitable part
of planning in a cool economic climate. The Community
Infrastructure Levy (CIL) is the latest attempt to capture land
value in the planning system. Although CIL started life as a
measure to broaden the base of those contributing to the costs of
the infrastructure required to support development, it has led to a
debate about who reaps the benefits, and who bears the costs, of
the allocations the system makes.
What is CIL and why does it matter?
CIL is a charge that local authorities may levy on new
development in their area. CIL was originally introduced (under the
Planning Act 2008) to be spent on providing infrastructure to
support development, but can now be spent on maintaining and
operating that infrastructure too. Section 205 of the 2008 Act
confirms its overall purpose as ensuring the costs of
infrastructure, to support the development of an area, can be met
(wholly or partly) by owners or developers of land in a way
that does not make development of the area economically
unviable (italics added by the Localism Act 2011).
CIL was intended to enable more money to be raised to fund
infrastructure than Section 106 agreements legally allow (see below). The CIL Final
Impact Assessment (CLG, February 2010) revealed that only around 6%
of permissions make s106 contributions. As well as offering a
source of extra funds (estimated by the last government as £700m
per year), CIL should also offer a more certain and transparent
basis for developers to price schemes.
CIL controls
In preparing to adopt CIL, charging authorities must comply with
the regulatory requirements as modified by the Localism Act,
including the appointment of an independent examiner (see below).
The process is relatively straightforward (see below). Charging authorities must
decide the appropriate balance between infrastructure gap funding
and development viability in their area and "how much" potential
development they are willing to put at risk through the imposition
of CIL.
Following the Localism Act's reforms to the CIL regime, the
examiner's role is to consider whether the charging authority has
complied with the "drafting requirements" under Part 11 of the 2008
Act and the CIL Regulations 2010. In particular, by using evidence
to identify the infrastructure funding gap that could be met by
CIL, to determine whether an appropriate balance has been
achieved.
The Localism Act now confirms that development must still,
overall, be viable, and there must be appropriate evidence
confirming that development of the area, in line with the
up–to–date development plan, has not been put at "serious risk".
Government guidance dictates that in considering whether the
development plan and its targets have been put at serious risk,
examiners should only consider whether the proposed CIL rate will
make a material or significant difference to the level of risk (on
the basis that the development plan and its targets could already
be at serious risk in the absence of CIL).
Any recommended modifications to the draft charging schedule
made by the examiner will no longer be binding on the charging
authority, unless it is rejected for adoption. Even then, the
Localism Act reforms mean that an authority may find its own route
to redemption and correct errors itself to enable adoption.
Crucially, with limited exceptions, CIL is non–negotiable
(see below). As a
result, and in combination with s106 continuing to cast a shadow
on appraisals, the development sector is recognising the importance
of both collaboration in, and thorough scrutiny of, the CIL setting
process.
Frontrunners
On 1 December 2011, Newark and Sherwood District Council adopted
the first CIL charging schedule. The council is now authorised to
charge new development at its published rates. As a result, it may
no longer treat any s106 obligations that secure infrastructure on
its published list as a reason for granting consent. Similarly, it
cannot take account of more than five post–April 2010 contributions
to the same infrastructure as a reason for approval.
This is intended to inhibit, if not prevent, planning
authorities asking for planning contributions to infrastructure
that should be paid within CIL. Once regulations (via the Localism
Act) come into force, charging authorities must also pass a
"meaningful proportion" of CIL receipts to parish councils.
Other frontrunners are close behind (see below) and include the mayor
of London. If mayoral CIL is adopted in April, development in
London boroughs will be charged at £20 to £50 per m2 to raise £300m
for Crossrail until 2018. In setting their own CILs and applying
s106, boroughs will then have to factor in the overall effect on
development viability. In many areas (including those that gain
little directly from Crossrail), the impact will be significant.
The mayoral CIL is expected to net around £40m per year and
Croydon's emerging charge is expected to take its planning–related
receipts from £2m (via s106) to £7m per year. Because CIL will not
replace all s106 requirements, there is every reason for those
interested in delivering development to scrutinise the
charge–setting process.
Lessons learned
The frontrunners have already shown that there are good reasons
to be vigilant. CIL rates may be differentiated by type of use and
by area. The guidance says such differences must be restricted to
viability reasons alone. At Newark and Sherwood, the examiner
rejected differential rates for "large" and "small" retail units
without "a very clear viability justification" for such rates, that
"could be said to unreasonably favour smaller retailers over larger
ones and/or constitute a policy decision by the charging authority
to support smaller units".
The mayoral CIL is a further example of the difficulties that
can arise where insufficient attention is paid to the rationale for
the amount of infrastructure for which CIL is to be used and the
reasons for setting differential rates. The guidance confirms that,
in identifying the cost of infrastructure they wish to fund from
CIL, charging authorities "will want to" consider what additional
infrastructure is needed in their area to support development and
what other funding sources are available. The mayor's charging
schedule sets out to fund the whole of the costs of Crossrail from
CIL and will require all boroughs to contribute, regardless of
their relationship to the Crossrail infrastructure.
Two main issues arise from this. First, whether adequate
attention has been paid to the desirability of funding either the
whole or just a part of the Crossrail cost from CIL. Second, where
different charges are levied in different areas, there needs to be
clear evidence that there are no state aid issues. While the
relationship between development in an area and Crossrail might
have justified different charges, the mayor rejected this approach
as a basis for setting differential charges. He is instead relying
on house price differences as a proxy.
CIL is payable in one hit, unless charging authorities adopt a
statement allowing payments by instalment. Unhappily, the statement
is not considered in the CIL setting process and can be changed or
reviewed at any time. An issue highlighted as part of the mayoral
CIL examination is the oddity that where there is a borough
instalment policy in place, this may govern, even if the mayor had
already published an earlier conflicting one. This potentially
gives real power to the boroughs, which could publish an instalment
policy that dictates the payment timetable for the mayoral CIL.
Future of Section 106
Section 106 obligations will not die. Evidence suggests they
will be reborn, as authorities ensure they have clear policy
justification (in local plans and supplementary planning documents)
for site specific mitigation and "softer" types of contributions
(ie, those not within the scope of CIL, such as employment and
training contributions).
The regulations introduce an event horizon for s106. Once CIL is
adopted, planning obligations must not be a "reason for approval"
where they concern things on an authority's published r123
infrastructure list. Nor may they be a reason for approval if they
seek to pool more than five CIL–able obligations (including those
since April 2010). For authorities that have not adopted CIL,
similar restrictions will apply after 6 April 2014.
As well as participating in the CIL process itself, developers
and their advisers will therefore need to monitor this use of
policy to avoid "double dipping" – being asked to pay under CIL and
under planning agreements. At the same time, authorities will need
to be careful about what they include on their published
infrastructure list. For every type of development it mentions,
s106 is intended by the Department for Communities and Local
Government to be unavailable under regulation 123(2). Being very
specific and limited about the projects mentioned preserves the
ability to use the full range of powers where appropriate.
Further consultation
The government has recently consulted on further reform of the
CIL regulatory framework. We wait to see how it will legislate to
pass money that was intended to deliver essential strategic
infrastructure to neighbourhood bodies. The option to re–introduce
affordable housing as a category on which CIL can be spent also
raises some difficulties. In practice, it is likely that although
more cash would be raised, less affordable housing, and less
mixed–tenure developments, would result. That would be a poor
planning outcome.
Continuing weaknesses
Several areas need further reform. First, the regulatory
framework should work to secure delivery of infrastructure. At the
moment it does not – authorities may simply pass on CIL receipts,
even if they are not actually used to deliver infrastructure.
Similarly, developers should be entitled to expect that Grampian
conditions (restricting development until delivery of specific
infrastructure) will only be permissible where they match
timescales in the authority's delivery programme.
Second, far better guidance is needed to assist promotion of
area regeneration by setting CIL at a level that will boost
investment. The guidance currently states that differential rates
"need to be justified by reference to the economic viability of
development". Given the regulatory context, that is not surprising,
but the statement in the guidance that "charging authorities should
not set differential rates by reference to the costs of
infrastructure, either in different zones or for different classes
of development" is policy, not law. An allocation of CIL based on
impact, or other patterns that do not directly stem from viability
differences, is legally permissible. In some cases it will be
entirely sensible.
What differential rates must not do is fall foul of the state
aid rules that generally prohibit selective advantage being
conferred on economic undertakings. The recent preliminary charging
schedule for Croydon, for example, will need to include far greater
justification for the "central area" rate it proposes.
Authorities can accept "payment in kind" for CIL liabilities and
the previous minimum threshold (£50,000) has been removed. However,
the credit is still only the value of land transferred (and not the
cost of any works that have been undertaken).
Conclusion
CIL has changed since 2008. It was meant to broaden the base of
contributors to infrastructure and ensure that even developments
with small impacts contribute. It was also meant to ensure
infrastructure delivery and wipe out planning agreements other than
for affordable housing and site–specific obligations. Although CIL
ensures broad–based contributions, payment is normally on the basis
of ability to pay, rather than being broadly related to the
infrastructure needs generated by that class of development.
Although not a charge "to the margins of viability" (at least not
yet) it has moved away from an impact fee towards a value–capture
mechanism.
It offers no comfort that the infrastructure needed to support
development will actually be provided. Indeed, that aim has been
undermined as money can be diverted to operation and maintenance of
infrastructure, and part will be paid across for the use of local
communities. The proposed protections against "double dipping" are
not wholly effective. Disappointingly, a raft of CIL charging
schedules and arrangements are being put in place that deliver too
little. With relatively limited changes, CIL could be made to work
far better.
Originally published in Estates Gazette, 28 January
2012.
| Section 106 and CIL |
| Section 106 |
CIL |
- Cannot be used to "buy or sell permissions" (Bradford City
Metropolitan Council v SoS [1986] 1 EGLR 199 and R (Plymouth and
South Devon Co–operative Society Ltd) v Plymouth City Council
(1993) 67 P & CR 78).
- The scale of contributions is a matter for the decision–maker,
not the courts, as long as there is a more than minimal
relationship between the obligation and the development (Tesco
Stores Ltd v Secretary of State for the Environment [1995] 1 WLR
759).
- Government policy controls (Circular 05/2005), requiring
obligations to be necessary, fairly and reasonably related to the
development, are flexibly applied in practice.
- Some tariff schemes (Milton Keynes "roof tax") have made
charging more consistent, but elsewhere the need to show that s106
levies are justified, effective and consistent with national policy
(including the tests in 05/05) has proved too much (the secretary
of state's rejection of the Kent Thameside Strategic Transport
Tariff in 2009).
|
- Non–negotiable floorspace levy based on a charging schedule
setting out a £ per m2 rate payable (subject to indexation).
- Applies to almost all permissions (including some permitted
development) for new developments of 100m2 or more of net
additional internal floorspace or one or more dwelling.
- Payable within 60 days of commencement, but instalments and
payments in kind may be allowed (plus very limited exemptions and
exceptions).
- Value capture, but hypothecated for area–wide
infrastructure.
- Up–to–date local plan required (or tandem development with core
strategy).
|
| CIL process |
- Charge–setting: identify total infrastructure cost associated
with expected development; identify the funding gap in light of
other sources of funding; and understand the effect of recovering
the whole or different levels of this through CIL (having
particular regard to the effect on development viability in the
areas as a whole).
- Consultation: publication of a preliminary draft charging
schedule and re–consultation on a revised draft charging schedule
(with a further opportunity to modify the draft)
- Examination (c. 20 weeks): appointment of an independent
examiner, consideration of recommendations and any
modifications.
- Adoption.
- Collect CIL, subject to any payments in kind.
- Apply the CIL revenue to funding infrastructure to support the
development of its area.
- Report to the local community on the amount of CIL revenue
collected, spent and retained each year, and pass a "meaningful
proportion" to the community.
|
| |
| Regulatory
framework |
| Community Infrastructure
Levy Regulations 2010 (as amended by the Community Infrastructure
Levy (Amendment) Regulations 2011) |
- r. 61(1): CIL funding of administrative expenses capped at 1 %
of CIL receipts plus 4% for costs of collection, although
consultation proposes removal of the cap.
- r.13: permits differential rates for zones or uses and
associated supplementary charges, nil rates, increased rates or
reductions.
- r.14: rate–setting authorities must aim to strike an
appropriate balance between the desirability of funding
infrastructure from CIL and the potential effects of the imposition
of CIL on the economic viability of development across their
areas.
- r.43: social housing and development by charities of their own
land for their charitable purposes are exempt from CIL.
- r.122: CIL–able obligations cannot be a "reason for approval"
of planning unless they are Circular 05/2005–compliant.
- r.123: from the date on which a charging schedule is adopted
(or 6 April 2014, if earlier) items on the published infrastructure
list (or any infrastructure pooled more than five times) cannot be
a reason for approval.
|
| Part 11 Planning Act 2008 |
Localism Act 2011 |
- s.205: must ensure viability.
- s.211(6): authorises differential rates in accordance with CIL
Regulations 2010.
- s.212(4): must use appropriate available evidence.
- s.221: requirement to have regard to CIL guidance: charge
setting and charging schedule procedures (CLG, 25 March 2010).
|
- s.114: more discretion for authorities not to adopt examiner's
recommendations. The government may make regulations fine tuning
evidence requirements in light of frontrunner experiences.
- s.115: "meaningful proportion" of CIL must be passed to
neighbourhoods and CIL may be spent on improving, replacing,
operating and maintaining infrastructure as well as initially
providing it.
|
| |
|
| Viability
exceptions |
- Public notice of the charging authority's intention to give
relief create
- Claims for relief on chargeable developments considered from
landowners on a case–by–case basis. In each case, an independent
person with suitable qualifications and experience must be
appointed by the claimant with the agreement of the charging
authority to assess whether:
- the cost of complying with Section 106 agreement obligations is
greater than the levy's charge on the development;
- paying the full CIL charge would have an unacceptable impact on
the development's economic viability.
- Relief must not constitute a notifiable state aid.
|
| |
| CIL frontrunners |
Newark and Sherwood District Council: Adopted 1 December 2011.
Eight zones with varying rates, up to £75 per m² (residential) and
£100 per m² flat rate (retail) apart from the £125 per m² Newark
Growth Point rate. Limited industrial charges up to £15m², in two
zones.
Shropshire Council: Adopted 1 January 2012. £40 to £80 per m² for
residential, £70 per sq m flat rate for other, not
employment.
LB Redbridge: Adopted 1 January 2012. £70 per m² borough–wide flat
rate.
Greater London Authority: Examination completed. If successful, it
intends charging to commence on 1 April 2012, £20 to £50 per m²
flat rate, by zone.
Colchester Borough Council: Preliminary draft published. £120 per
m² (residential), £90 per m² (comparison retail), £240 per m²
(convenience retail).
Croydon: Preliminary draft charging schedule published. Zonal and
use–differential rates, £0 to 120 per m². |
| |