Mail to a Colleague

All fields are mandatory and must be completed.

    

Mail to a Colleague

Thank you. Your message has been sent to your colleague.

The Year of the Community Infrastructure Levy

January 31, 2012

Debates over viability and value ­capture are an inevitable part of planning in a cool economic climate. The Community Infrastructure Levy (CIL) is the latest attempt to capture land value in the planning system. Although CIL started life as a measure to broaden the base of those contributing to the costs of the infrastructure required to support development, it has led to a debate about who reaps the benefits, and who bears the costs, of the allocations the system makes.

What is CIL and why does it matter?

CIL is a charge that local authorities may levy on new development in their area. CIL was originally introduced (under the Planning Act 2008) to be spent on providing infrastructure to support development, but can now be spent on maintaining and operating that infrastructure too. Section 205 of the 2008 Act confirms its overall purpose as ensuring the costs of infrastructure, to support the development of an area, can be met (wholly or partly) by owners or developers of land in a way that does not make development of the area economically unviable (italics added by the Localism Act 2011).

CIL was intended to enable more money to be raised to fund infrastructure than Section 106 agreements legally allow (see below). The CIL Final Impact Assessment (CLG, February 2010) revealed that only around 6% of permissions make s106 contributions. As well as offering a source of extra funds (estimated by the last government as £700m per year), CIL should also offer a more certain and transparent basis for developers to price schemes.

CIL controls

In preparing to adopt CIL, charging authorities must comply with the regulatory requirements as modified by the Localism Act, including the appointment of an independent examiner (see below).

The process is relatively straightforward (see below). Charging authorities must decide the appropriate balance between infrastructure gap funding and development viability in their area and "how much" potential development they are willing to put at risk through the imposition of CIL.

Following the Localism Act's reforms to the CIL regime, the examiner's role is to consider whether the charging authority has complied with the "drafting requirements" under Part 11 of the 2008 Act and the CIL Regulations 2010. In particular, by using evidence to identify the infrastructure funding gap that could be met by CIL, to determine whether an appropriate balance has been achieved.

The Localism Act now confirms that development must still, overall, be viable, and there must be appropriate evidence confirming that development of the area, in line with the up–to–date development plan, has not been put at "serious risk". Government guidance dictates that in considering whether the development plan and its targets have been put at serious risk, examiners should only consider whether the proposed CIL rate will make a material or significant difference to the level of risk (on the basis that the development plan and its targets could already be at serious risk in the absence of CIL).

Any recommended modifications to the draft charging schedule made by the examiner will no longer be binding on the charging authority, unless it is rejected for adoption. Even then, the Localism Act reforms mean that an authority may find its own route to redemption and correct errors itself to enable adoption.

Crucially, with limited exceptions, CIL is non–negotiable (see below). As a result, and in combination with s106 ­continuing to cast a shadow on appraisals, the development sector is recognising the importance of both collaboration in, and thorough scrutiny of, the CIL setting process.

Frontrunners

On 1 December 2011, Newark and Sherwood District Council adopted the first CIL charging schedule. The council is now authorised to charge new development at its published rates. As a result, it may no longer treat any s106 obligations that secure infrastructure on its published list as a reason for granting consent. Similarly, it cannot take account of more than five post–April 2010 contributions to the same infrastructure as a reason for approval.

This is intended to inhibit, if not prevent, planning authorities asking for planning contributions to infrastructure that should be paid within CIL. Once regulations (via the Localism Act) come into force, charging authorities must also pass a "meaningful proportion" of CIL receipts to parish councils.

Other frontrunners are close behind (see below) and include the mayor of London. If mayoral CIL is adopted in April, development in London boroughs will be charged at £20 to £50 per m2 to raise £300m for Crossrail until 2018. In setting their own CILs and applying s106, boroughs will then have to factor in the overall effect on development viability. In many areas (including those that gain little directly from Crossrail), the impact will be significant. The mayoral CIL is expected to net around £40m per year and Croydon's emerging charge is expected to take its planning–related receipts from £2m (via s106) to £7m per year. Because CIL will not replace all s106 requirements, there is every reason for those interested in delivering development to scrutinise the charge–setting process.

Lessons learned

The frontrunners have already shown that there are good reasons to be vigilant. CIL rates may be differentiated by type of use and by area. The guidance says such differences must be restricted to viability reasons alone. At Newark and Sherwood, the examiner rejected differential rates for "large" and "small" retail units without "a very clear viability justification" for such rates, that "could be said to unreasonably favour smaller retailers over larger ones and/or constitute a policy decision by the charging authority to support smaller units".

The mayoral CIL is a further example of the difficulties that can arise where insufficient attention is paid to the rationale for the amount of infrastructure for which CIL is to be used and the reasons for setting differential rates. The guidance confirms that, in identifying the cost of infrastructure they wish to fund from CIL, charging authorities "will want to" consider what additional infrastructure is needed in their area to support development and what other funding sources are available. The mayor's charging schedule sets out to fund the whole of the costs of Crossrail from CIL and will require all boroughs to contribute, regardless of their relationship to the Crossrail infrastructure.

Two main issues arise from this. First, whether adequate attention has been paid to the desirability of funding either the whole or just a part of the Crossrail cost from CIL. Second, where different charges are levied in different areas, there needs to be clear evidence that there are no state aid issues. While the relationship between development in an area and Crossrail might have justified different charges, the mayor rejected this approach as a basis for setting differential charges. He is instead relying on house price differences as a proxy.

CIL is payable in one hit, unless charging authorities adopt a statement allowing payments by instalment. Unhappily, the statement is not considered in the CIL setting process and can be changed or reviewed at any time. An issue highlighted as part of the mayoral CIL examination is the oddity that where there is a borough instalment policy in place, this may govern, even if the mayor had already published an earlier conflicting one. This potentially gives real power to the boroughs, which could publish an instalment policy that dictates the payment timetable for the mayoral CIL.

Future of Section 106

Section 106 obligations will not die. Evidence suggests they will be reborn, as authorities ensure they have clear policy justification (in local plans and supplementary planning documents) for site specific mitigation and "softer" types of contributions (ie, those not within the scope of CIL, such as employment and training contributions).

The regulations introduce an event horizon for s106. Once CIL is adopted, planning obligations must not be a "reason for approval" where they concern things on an authority's published r123 infrastructure list. Nor may they be a reason for approval if they seek to pool more than five CIL–able obligations (including those since April 2010). For authorities that have not adopted CIL, similar restrictions will apply after 6 April 2014.

As well as participating in the CIL process itself, developers and their advisers will therefore need to monitor this use of policy to avoid "double dipping" – being asked to pay under CIL and under planning agreements. At the same time, authorities will need to be careful about what they include on their published infrastructure list. For every type of development it mentions, s106 is intended by the Department for Communities and Local Government to be unavailable under regulation 123(2). Being very specific and limited about the projects mentioned preserves the ability to use the full range of powers where appropriate.

Further consultation

The government has recently consulted on further reform of the CIL regulatory framework. We wait to see how it will legislate to pass money that was intended to deliver essential strategic infrastructure to neighbourhood bodies. The option to re–introduce affordable housing as a category on which CIL can be spent also raises some difficulties. In practice, it is likely that although more cash would be raised, less affordable housing, and less mixed–tenure developments, would result. That would be a poor planning outcome.

Continuing weaknesses

Several areas need further reform. First, the regulatory framework should work to secure delivery of infrastructure. At the moment it does not – authorities may simply pass on CIL receipts, even if they are not actually used to deliver infrastructure. Similarly, developers should be entitled to expect that Grampian conditions (restricting development until delivery of specific infrastructure) will only be permissible where they match timescales in the authority's delivery programme.

Second, far better guidance is needed to assist promotion of area regeneration by setting CIL at a level that will boost investment. The guidance currently states that differential rates "need to be justified by reference to the economic viability of development". Given the regulatory context, that is not surprising, but the statement in the guidance that "charging authorities should not set differential rates by reference to the costs of infrastructure, either in different zones or for different classes of development" is policy, not law. An allocation of CIL based on impact, or other patterns that do not directly stem from viability differences, is legally permissible. In some cases it will be entirely sensible.

What differential rates must not do is fall foul of the state aid rules that generally prohibit selective advantage being conferred on economic undertakings. The recent preliminary charging schedule for Croydon, for example, will need to include far greater justification for the "central area" rate it proposes.

Authorities can accept "payment in kind" for CIL liabilities and the previous minimum threshold (£50,000) has been removed. However, the credit is still only the value of land transferred (and not the cost of any works that have been undertaken).

Conclusion

CIL has changed since 2008. It was meant to broaden the base of contributors to infrastructure and ensure that even developments with small impacts contribute. It was also meant to ensure infrastructure delivery and wipe out planning agreements other than for affordable housing and site–specific obligations. Although CIL ensures broad–based contributions, payment is normally on the basis of ability to pay, rather than being broadly related to the infrastructure needs generated by that class of development. Although not a charge "to the margins of viability" (at least not yet) it has moved away from an impact fee towards a value–capture mechanism.

It offers no comfort that the infrastructure needed to support development will actually be provided. Indeed, that aim has been undermined as money can be diverted to operation and maintenance of infra­structure, and part will be paid across for the use of local communities. The proposed protections against "double dipping" are not wholly effective. Disappointingly, a raft of CIL charging schedules and arrangements are being put in place that deliver too little. With relatively limited changes, CIL could be made to work far better.

Originally published in Estates Gazette, 28 January 2012.


Section 106 and CIL
Section 106 CIL
  • Cannot be used to "buy or sell permissions" (Bradford City Metropolitan Council v SoS [1986] 1 EGLR 199 and R (Plymouth and South Devon Co–operative Society Ltd) v Plymouth City Council (1993) 67 P & CR 78).
  • The scale of contributions is a matter for the decision–maker, not the courts, as long as there is a more than minimal relationship between the obligation and the development (Tesco Stores Ltd v Secretary of State for the Environment [1995] 1 WLR 759).
  • Government policy controls (Circular 05/2005), requiring obligations to be necessary, fairly and reasonably related to the development, are flexibly applied in practice.
  • Some tariff schemes (Milton Keynes "roof tax") have made charging more consistent, but elsewhere the need to show that s106 levies are justified, effective and consistent with national policy (including the tests in 05/05) has proved too much (the secretary of state's rejection of the Kent Thameside Strategic Transport Tariff in 2009).
  • Non–negotiable floorspace levy based on a charging schedule setting out a £ per m2 rate payable (subject to indexation).
  • Applies to almost all permissions (including some permitted development) for new developments of 100m2 or more of net additional internal floorspace or one or more dwelling.
  • Payable within 60 days of commencement, but instalments and payments in kind may be allowed (plus very limited exemptions and exceptions).
  • Value capture, but hypothecated for area–wide infrastructure.
  • Up–to–date local plan required (or tandem development with core strategy).
CIL process
  • Charge–setting: identify total infrastructure cost associated with expected development; identify the funding gap in light of other sources of funding; and understand the effect of recovering the whole or different levels of this through CIL (having particular regard to the effect on development viability in the areas as a whole).
  • Consultation: publication of a preliminary draft charging schedule and re–consultation on a revised draft charging schedule (with a further opportunity to modify the draft)
  • Examination (c. 20 weeks): appointment of an independent examiner, consideration of recommendations and any modifications.
  • Adoption.
  • Collect CIL, subject to any payments in kind.
  • Apply the CIL revenue to funding infrastructure to support the development of its area.
  • Report to the local community on the amount of CIL revenue collected, spent and retained each year, and pass a "meaningful proportion" to the community.
 
Regulatory framework
Community Infrastructure Levy Regulations 2010 (as amended by the Community Infrastructure Levy (Amendment) Regulations 2011)
  • r. 61(1): CIL funding of administrative expenses capped at 1 % of CIL receipts plus 4% for costs of collection, although consultation proposes removal of the cap.
  • r.13: permits differential rates for zones or uses and associated supplementary charges, nil rates, increased rates or reductions.
  • r.14: rate–setting authorities must aim to strike an appropriate balance between the desirability of funding infrastructure from CIL and the potential effects of the imposition of CIL on the economic viability of development across their areas.
  • r.43: social housing and development by charities of their own land for their charitable purposes are exempt from CIL.
  • r.122: CIL–able obligations cannot be a "reason for approval" of planning unless they are Circular 05/2005–compliant.
  • r.123: from the date on which a charging schedule is adopted (or 6 April 2014, if earlier) items on the published infrastructure list (or any infrastructure pooled more than five times) cannot be a reason for approval.
Part 11 Planning Act 2008 Localism Act 2011
  • s.205: must ensure viability.
  • s.211(6): authorises differential rates in accordance with CIL Regulations 2010.
  • s.212(4): must use appropriate available evidence.
  • s.221: requirement to have regard to CIL guidance: charge setting and charging schedule procedures (CLG, 25 March 2010).
  • s.114: more discretion for authorities not to adopt examiner's recommendations. The government may make regulations fine tuning evidence requirements in light of frontrunner experiences.
  • s.115: "meaningful proportion" of CIL must be passed to neighbourhoods and CIL may be spent on improving, replacing, operating and maintaining infrastructure as well as initially providing it.
   
Viability exceptions
  • Public notice of the charging authority's intention to give relief create
  • Claims for relief on chargeable developments considered from landowners on a case–by–case basis. In each case, an independent person with suitable qualifications and experience must be appointed by the claimant with the agreement of the charging authority to assess whether:
    • the cost of complying with Section 106 agreement obligations is greater than the levy's charge on the development;
    • paying the full CIL charge would have an unacceptable impact on the development's economic viability.
  • Relief must not constitute a notifiable state aid.
 
CIL frontrunners
Newark and Sherwood District Council: Adopted 1 December 2011. Eight zones with varying rates, up to £75 per m² (residential) and £100 per m² flat rate (retail) apart from the £125 per m² Newark Growth Point rate. Limited industrial charges up to £15m², in two zones.
Shropshire Council: Adopted 1 January 2012. £40 to £80 per m² for residential, £70 per sq m flat rate for other, not employment.
LB Redbridge: Adopted 1 January 2012. £70 per m² borough–wide flat rate.
Greater London Authority: Examination completed. If successful, it intends charging to commence on 1 April 2012, £20 to £50 per m² flat rate, by zone.
Colchester Borough Council: Preliminary draft published. £120 per m² (residential), £90 per m² (comparison retail), £240 per m² (convenience retail).
Croydon: Preliminary draft charging schedule published. Zonal and use–differential rates, £0 to 120 per m².
 
Key Contacts Contacts

Roy Pinnock
Senior Associate
London
D +44 (0)20 7246 7683
M +44 (0)7795 618 260
Email
roy.pinnock@snrdenton.com
Download vCard

Stephen Ashworth
Consultant
London
D +44 (0)20 7320 6134
M +44 (0)7771 842811
Email
stephen.ashworth@snrdenton.com
Download vCard

Disclaimer

Unsolicited e-mails and information sent to SNR Denton will not be considered confidential, may be disclosed to others, may not receive a response, and do not create a lawyer-client relationship with SNR Denton.

If you are not already a client of SNR Denton, please do not include any confidential information in this message.

Also, please note that our lawyers do not seek to practise law in any jurisdiction in which they are not properly permitted to do so.